measurements beyond deadline; define discreet boundaries for green, yellow, red status as % of plan deviation; keep list critical issues sorted by project delay
The saying goes that after more than two hierarchy levels of reporting, every project status becomes green because nobody likes to fail his boss. In my early years of consulting, when I was still glad that I didn’t have to do any status reporting, I experienced a lot of projects, where “meeting the deadline no matter what” meant everything. The first thing that went was functionality. If that didn’t work, quality of deliverables was reduced, and if the deadline still seemed to ambitious, we worked frantically through the night. All the time, the project status was at most a tish yellow, but never red. And it wasn’t even a lie: there was always something delivered at the due date.
I recently worked on a strategy project that was part of an Identity Management program at a tier 1 telecom operator and experienced the same thing again. The first milestone of the program totally bombed: everyone delivered in time, but all executives were dissatisfied with the result. When reviewing with the program management office what went wrong, we discovered that there were very little tangible measurements in place other than “do we make the deadline” – which is by the way a very binary question: I wonder how you can meet the deadline half without any other measurement such as work packages, time, resources…
We came up with a couple of measurable items that worked for us:
While some of the things from the previous list are relatively easy to measure, such as the number of documents or divisions involved or person days billed against the project. Others are more tricky: How do I assess the severity of risks? To what degree is a program goal currently satisfied? Do we measure work packages by the number of sub-tasks we finished, or by the difficulty of finishing these tasks?
Our solutions were very straight forward:
For each of the measurements we then defined boundaries of percentages of the planned values for different status levels. For example, for issues, risks, and other events that popped up during the project, everything that delayed the program more than seven days was a yellow item, everything more than 21 days was a red item. You get the picture.
The result was a steering committee dashboard, covering time, resources, work in progress, and a list of items and events each with its impact on time and resources attached. It told the committee where we were right now, and where we would be if we kept the course. Now the steering committee was able to take actions: revise the plan, call in people who could help, or take other counter measurements. The dashboard was never intended to directly stop or change work packages, or make strategic and tactical decisions, but to support the steering committee in these tasks and revisit the plan, making decisions and issues transparent.
You can follow the comments for this article with the RSS 2.0 feed.
Thanks for sharing this post
Content © Playout Intelligence
Proudly powered by WordPress
Theme designed by Artisan Themes
Hello Guru, what entice you to post an article on l Status Reporting in Project and Program Management | Playout Intelligence? This article was extremely interesting, especially since I was searching for thoughts on this subject last Saturday.